on 01-25-2011 9:57 PM
I have a planning area that i'm not able to transfer the demand to ECC. All of the release profile, transfer activity and background job are set up correctly.
After we run the background job the log shows that the transfer is successful. If i check in md62 there is no forecast update.
The integration model is set up in ECC for the products I want to transfer.
Suggestions please....
Hi Paul,
Assuming this to be standard system with no enhancements to outbound and inbound CIF objects, could you check the entries in Publication settings in IMG..if planned independent requirements object and its location are specified for publication back to the source logical system
t:code to save time: S_AP3_40000005
Regards,
Loknath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Extended the calendar 2 years prior to the required date which resolved the problem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes there were some CIF errors that need to be cleared which we done and all appears to be okay.
Next error in the CIF is "01.01.2008 date lies before start of factory calendar" but I'vre checked this and they start on 01.01.2007.
Does anyone know how to fix this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Loknath.
planned independent requirements object and the location was not set up. This plant is now set up (yes this is a new plant) but the transfer still doesn't work.
Where to from here?
Thanks
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just a guess again. See if the requirement is flowing to another node. e.g. ship-to-party in which case PIR's may not be seen against MATR-WERKS but material-ship to or material-sold to with ship to and/ir sold to being customer locations in APO on which PIR's are intended design. May be the product and location are known with a different name in ECC e.g. as with mapping some other external locations and products
Run CCR on PIR's and see the error code against the PIR documents. check any inbound CIF enhancements to ECC and/or outbound to APO.
Regards,
Loknath
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.