on 01-25-2011 4:11 PM
The xRPM system is showing 56 hours as the number of hours resources are available to work. This needs to be 40. Presumption is that Saturday and Sundar are deemed working days, and they shouldn't be.
I know this is a basic fix. However, am new to this and not sure how to resolve. Would appreciate any assistance. Thx.
tcode: RPM_EMPDATA
Here's where you can store/view such BP information as availability, qualification, location etc.
See how the availability has been defined for the BP in question...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is based on the calendar that is used. The system will check this in the following order...
1. From the location of the BP (when you define locations you can specify a calendar for each location)
2. location of the role
3. setting in IMG option "Make General Settings for Distribution" under Project Management > Res Mgt > Basic Settings for Roles