i am working in a Power Corporation industry, and we have sum sub contactors who returned some of the materials,supplies which wer issued by us,they have presented a credit note to us indicating why they return their materials to us .so i do not know what exactly the process to follow in order to correct these problem.pls help
Dear,
This seems like a VENDOR RETURN process.
The steps are following,
- Create a return PO with Tcode ME21N ( just one return check box at line item)
- Recd material Tcode = MIGO and movement type = 161
- Credit processing using Tcode = MIRO and option = credit ( this on top).
Hope this help.
thx
Dilip Sadh