Maintenance Plan - Avoid maintenance dates in the past

Former Member
0 Kudos

Hi gurus,

I have a requirement that I dont know how to solve it.

I our maintenance plan (Based on days and activity) we need to avoid dates in the past when we start the plan (IP10).

We've noticed that sometimes in days based plans, after start in IP10, some records for dates in past appears.

Example:

If we start a plan in 01.01.2011 and cycle is at 10 days we get this:

ABNUM NPLDA

1- 11.01.2011

2- 21.01.2011

3- 31.01.2011

We dont need records 1 and 2, because it planned date is in past.

Is there any way to avoid this records in past?? Our ideal behaviour will be as the following, with no past dates.

ABNUM NPLDA

1- 31.01.2011

Thanks in advance.

Edited by: Ole ES on Jan 25, 2011 7:32 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Solved using IPRM0004 user-exit.