SPM - Transport Question

0 Kudos

Hi:

Is it possible to capture dimension/measure (making it visible/in-visible) that is done at SPM UI end and transport them thru' the landscape?

If so, how do we do that?

If not, what is the best way to keep all the environment in sync for properties maintained at SPM UI level?

Thanks and Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Yes any changes made in the UI like dimension / measure properties can be captured in a transport and moved to other systems. Use the program "OPM_PS_TRANSPORT" in SPM 2.1 to capture your changes.

Regards,

Rohit

Former Member
0 Kudos

Hi Rohit,

Is there any specific way to transport the Customer specific Tree maintined under Groups folder in UI to Q and Production systems. We are facing issue with the report transportation to Quality.

Thank you

Best regards,

Amarnath