Dear Team,
At the time of Patch uptdate in BI server the patch of BI_CONT is stuck in XPRA_EXECUTION phase i am trying to re start the queue again but it stuck at same stage again can u help in this issue server detail as follows.
OS -- AIX
DB - Oracle
Component version - SAP NetWeaver 2004s
Sanjeev
Dear Friend,
Pls find the log
Import phase 'XPRA_EXECUTION' (20.01.2011, 16:13:26)
Error during executing the tp command 'tp XPA ALL JBQ ...'
tp return code: '0008' , tp message: 'A tool used by tp produced errors , tp output:
This is tp version 372.04.70 (release 700, unicode enabled)
Warning: Parameter DBLIBPATH is no longer used.
standard output from tp and from tools called by tp:
Details of the error situation can also be found in the import logs
Interrupt the import due to an error situation (20.01.2011, 16:15:02)
Display detailed informations concerning the error in phase 'XPRA_EXE
Abort the import due to an error situation (20.01.2011, 16:23:10)
Sanjeev
Edited by: Sanjeev Mishra on Jan 24, 2011 8:33 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nirmal,
Saving the current OCS Queue (19.01.2011, 23:22:23)
001: SAPKIBIIQ4 - Support Package for BI_CONT Release 703
002: SAPKIBIIQ5 - Support Package for BI_CONT Release 703
003: SAPKIBIIQ6 - Support Package for BI_CONT Release 703
Import of the current OCS Queue (19.01.2011, 23:22:31)
The import is done with the Standard scenario
The current OCS Queue consists of:
001: SAPKIBIIQ4
002: SAPKIBIIQ5
003: SAPKIBIIQ6
Display notes, which should be considered before the start of the import
Note 955647 for OCS Package SAPKIBIIQ4
Note 955647 for OCS Package SAPKIBIIQ5
Note 955647 for OCS Package SAPKIBIIQ6
Execute check steps before scheduling the import job
Import phase 'PROLOGUE' (19.01.2011, 23:22:50)
Import phase 'PROLOGUE' was successfully finished (19.01.2011, 23:22:50)
Import phase 'CHECK_REQUIREMENTS' (19.01.2011, 23:22:50)
Import phase 'CHECK_REQUIREMENTS' was successfully finished (19.01.2011, 23:22:52)
The execution of the check steps finished successfully (19.01.2011, 23:22:52)
Schedule the import for background processing (for immediate start)
Job OCS_QUEUE_IMPORT scheduled
Import of the current OCS Queue in background (19.01.2011, 23:22:52)
The import is done with the Standard scenario
The import is continued in phase 'CHECK_REQUIREMENTS'
The current OCS Queue consists of:
001: SAPKIBIIQ4 - Support Package for BI_CONT Release 703
002: SAPKIBIIQ5 - Support Package for BI_CONT Release 703
003: SAPKIBIIQ6 - Support Package for BI_CONT Release 703
Import phase 'PROLOGUE' (19.01.2011, 23:22:52)
Import phase 'PROLOGUE' was successfully finished (19.01.2011, 23:22:52)
Import phase 'CHECK_REQUIREMENTS' (19.01.2011, 23:22:52)
Import phase 'CHECK_REQUIREMENTS' was successfully finished (19.01.2011, 23:22:52)
Import phase 'DISASSEMBLE' (19.01.2011, 23:22:52)
Import phase 'DISASSEMBLE' was successfully finished (19.01.2011, 23:22:58)
Import phase 'ADD_TO_BUFFER' (19.01.2011, 23:22:58)
Import phase 'ADD_TO_BUFFER' was successfully finished (19.01.2011, 23:22:58)
Import phase 'MODIFY_BUFFER' (19.01.2011, 23:22:58)
Import phase 'MODIFY_BUFFER' was successfully finished (19.01.2011, 23:22:59)
Import phase 'IMPORT_OBJECT_LIST' (19.01.2011, 23:22:59)
Import phase 'IMPORT_OBJECT_LIST' was successfully finished (19.01.2011, 23:23:11)
Import phase 'OBJECTS_LOCKED_?' (19.01.2011, 23:23:11)
Import phase 'OBJECTS_LOCKED_?' was successfully finished (19.01.2011, 23:23:13)
Import phase 'TEST_IMPORT' (19.01.2011, 23:23:13)
The test import of the queue finished with tp return code '0000'
Analyse the return codes of the individual packages...
The test import for SAPKIBIIQ4 finished error free
The test import for SAPKIBIIQ5 finished error free
The test import for SAPKIBIIQ6 finished error free
Import phase 'TEST_IMPORT' was successfully finished (19.01.2011, 23:23:22)
Import phase 'ADDON_CONFLICTS_?' (19.01.2011, 23:23:22)
Import phase 'ADDON_CONFLICTS_?' was successfully finished (19.01.2011, 23:23:22)
Import phase 'SCHEDULE_RDDIMPDP' (19.01.2011, 23:23:22)
Import phase 'SCHEDULE_RDDIMPDP' was successfully finished (19.01.2011, 23:23:22)
Import phase 'CREATE_VERS_BEFORE' (19.01.2011, 23:23:22)
Complete creation of version is switched off -> skip phase
Import phase 'SPDD_SPAU_CHECK' (19.01.2011, 23:23:22)
Import phase 'SPDD_SPAU_CHECK' was successfully finished (19.01.2011, 23:23:40)
Import phase 'DDIC_IMPORT' (19.01.2011, 23:23:40)
Import phase 'DDIC_IMPORT' was successfully finished (19.01.2011, 23:23:46)
Import phase 'AUTO_MOD_SPDD' (19.01.2011, 23:23:46)
Import phase 'AUTO_MOD_SPDD' was successfully finished (19.01.2011, 23:23:46)
Import phase 'RUN_SPDD_?' (19.01.2011, 23:23:46)
Import phase 'RUN_SPDD_?' was successfully finished (19.01.2011, 23:23:46)
Import phase 'DDIC_ACTIVATION' (19.01.2011, 23:23:46)
3T
Import phase 'IMPORT_PROPER' (19.01.2011, 23:23:50)
Import phase 'IMPORT_PROPER' was successfully finished (19.01.2011, 23:31:37)
Import phase 'PREPARE_XPRA' (19.01.2011, 23:31:37)
Import phase 'PREPARE_XPRA' was successfully finished (19.01.2011, 23:31:37)
Import phase 'AUTO_MOD_SPAU' (19.01.2011, 23:31:37)
Import phase 'AUTO_MOD_SPAU' was successfully finished (19.01.2011, 23:31:38)
Import phase 'XPRA_EXECUTION' (19.01.2011, 23:31:38)
8O Error during executing the tp command 'tp XPA ALL JBQ ...'
8O tp return code: '0008' , tp message: 'A tool used by tp produced errors' , tp output:
This is tp version 372.04.70 (release 700, unicode enabled)
Warning: Parameter DBLIBPATH is no longer used.
standard output from tp and from tools called by tp:
8O Details of the error situation can also be found in the import logs
8O Abort the import due to an error situation (19.01.2011, 23:38:34)
Import of the current OCS Queue (20.01.2011, 00:00:38)
The import is done with the Standard scenario
The import is continued in phase 'XPRA_EXECUTION'
The current OCS Queue consists of:
001: SAPKIBIIQ4
002: SAPKIBIIQ5
003: SAPKIBIIQ6
Import phase 'PROLOGUE' (20.01.2011, 00:00:46)
Import phase 'PROLOGUE' was successfully finished (20.01.2011, 00:00:47)
Import phase 'CHECK_REQUIREMENTS' (20.01.2011, 00:00:47)
Import phase 'CHECK_REQUIREMENTS' was successfully finished (20.01.2011, 00:00:47)
Import phase 'DISASSEMBLE' (20.01.2011, 00:00:47)
Import phase 'DISASSEMBLE' was already processed -> skip phase
Import phase 'ADD_TO_BUFFER' (20.01.2011, 00:00:47)
Import phase 'ADD_TO_BUFFER' was already processed -> skip phase
Import phase 'MODIFY_BUFFER' (20.01.2011, 00:00:47)
Import phase 'MODIFY_BUFFER' was already processed -> skip phase
Import phase 'IMPORT_OBJECT_LIST' (20.01.2011, 00:00:47)
Import phase 'IMPORT_OBJECT_LIST' was already processed -> skip phase
Import phase 'OBJECTS_LOCKED_?' (20.01.2011, 00:00:47)
Import phase 'OBJECTS_LOCKED_?' was already processed -> skip phase
Import phase 'TEST_IMPORT' (20.01.2011, 00:00:47)
Import phase 'TEST_IMPORT' was already processed -> skip phase
Import phase 'ADDON_CONFLICTS_?' (20.01.2011, 00:00:47)
Import phase 'ADDON_CONFLICTS_?' was already processed -> skip phase
Import phase 'SCHEDULE_RDDIMPDP' (20.01.2011, 00:00:47)
Import phase 'SCHEDULE_RDDIMPDP' was already processed -> skip phase
Import phase 'CREATE_VERS_BEFORE' (20.01.2011, 00:00:47)
Complete creation of version is switched off -> skip phase
Import phase 'SPDD_SPAU_CHECK' (20.01.2011, 00:00:47)
Import phase 'SPDD_SPAU_CHECK' was already processed -> skip phase
Import phase 'DDIC_IMPORT' (20.01.2011, 00:00:47)
Import phase 'DDIC_IMPORT' was already processed -> skip phase
Import phase 'AUTO_MOD_SPDD' (20.01.2011, 00:00:47)
Import phase 'AUTO_MOD_SPDD' was already processed -> skip phase
Import phase 'RUN_SPDD_?' (20.01.2011, 00:00:47)
Import phase 'RUN_SPDD_?' was already processed -> skip phase
Import phase 'DDIC_ACTIVATION' (20.01.2011, 00:00:47)
Import phase 'DDIC_ACTIVATION' was already processed -> skip phase
Import phase 'IMPORT_PROPER' (20.01.2011, 00:00:47)
Import phase 'IMPORT_PROPER' was already processed -> skip phase
Import phase 'PREPARE_XPRA' (20.01.2011, 00:00:47)
Import phase 'PREPARE_XPRA' was already processed -> skip phase
Import phase 'AUTO_MOD_SPAU' (20.01.2011, 00:00:47)
Import phase 'AUTO_MOD_SPAU' was already processed -> skip phase
Import phase 'XPRA_EXECUTION' (20.01.2011, 00:00:47)
8O Error during executing the tp command 'tp XPA ALL JBQ ...'
8O tp return code: '0008' , tp message: 'A tool used by tp produced errors' , tp output:
This is tp version 372.04.70 (release 700, unicode enabled)
Warning: Parameter DBLIBPATH is no longer used.
standard output from tp and from tools called by tp:
8O Details of the error situation can also be found in the import logs
8R Interrupt the import due to an error situation (20.01.2011, 00:02:23)
Display detailed informations concerning the error in phase 'XPRA_EXECUTION'
8O Abort the import due to an error situation (20.01.2011, 00:02:42)
Import of the current OCS Queue (20.01.2011, 00:03:22)
The import is done with the Standard scenario
The import is continued in phase 'XPRA_EXECUTION'
The current OCS Queue consists of:
001: SAPKIBIIQ4
002: SAPKIBIIQ5
003: SAPKIBIIQ6
Execute check steps before scheduling the import job
Import phase 'PROLOGUE' (20.01.2011, 00:03:33)
Import phase 'PROLOGUE' was successfully finished (20.01.2011, 00:03:33)
Import phase 'CHECK_REQUIREMENTS' (20.01.2011, 00:03:33)
Import phase 'CHECK_REQUIREMENTS' was successfully finished (20.01.2011, 00:03:33)
The execution of the check steps finished successfully (20.01.2011, 00:03:33)
Schedule the import for background processing (for immediate start)
Job OCS_QUEUE_IMPORT scheduled
Import of the current OCS Queue in background (20.01.2011, 00:04:04)
The import is done with the Standard scenario
The import is continued in phase 'XPRA_EXECUTION'
The current OCS Queue consists of:
001: SAPKIBIIQ4 - Support Package for BI_CONT Release 703
002: SAPKIBIIQ5 - Support Package for BI_CONT Release 703
003: SAPKIBIIQ6 - Support Package for BI_CONT Release 703
Import phase 'PROLOGUE' (20.01.2011, 00:04:04)
Import phase 'PROLOGUE' was successfully finished (20.01.2011, 00:04:04)
Import phase 'CHECK_REQUIREMENTS' (20.01.2011, 00:04:04)
Import phase 'CHECK_REQUIREMENTS' was successfully finished (20.01.2011, 00:04:04)
Import phase 'DISASSEMBLE' (20.01.2011, 00:04:04)
Import phase 'DISASSEMBLE' was already processed -> skip phase
Import phase 'ADD_TO_BUFFER' (20.01.2011, 00:04:04)
Import phase 'ADD_TO_BUFFER' was already processed -> skip phase
Import phase 'MODIFY_BUFFER' (20.01.2011, 00:04:04)
Import phase 'MODIFY_BUFFER' was already processed -> skip phase
Import phase 'IMPORT_OBJECT_LIST' (20.01.2011, 00:04:04)
Import phase 'IMPORT_OBJECT_LIST' was already processed -> skip phase
Import phase 'OBJECTS_LOCKED_?' (20.01.2011, 00:04:04)
Import phase 'OBJECTS_LOCKED_?' was already processed -> skip phase
Import phase 'TEST_IMPORT' (20.01.2011, 00:04:04)
Import phase 'TEST_IMPORT' was already processed -> skip phase
Import phase 'ADDON_CONFLICTS_?' (20.01.2011, 00:04:04)
Import phase 'ADDON_CONFLICTS_?' was already processed -> skip phase
Import phase 'SCHEDULE_RDDIMPDP' (20.01.2011, 00:04:04)
Import phase 'SCHEDULE_RDDIMPDP' was already processed -> skip phase
Import phase 'CREATE_VERS_BEFORE' (20.01.2011, 00:04:04)
Complete creation of version is switched off -> skip phase
Import phase 'SPDD_SPAU_CHECK' (20.01.2011, 00:04:04)
Import phase 'SPDD_SPAU_CHECK' was already processed -> skip phase
Import phase 'DDIC_IMPORT' (20.01.2011, 00:04:04)
Import phase 'DDIC_IMPORT' was already processed -> skip phase
Import phase 'AUTO_MOD_SPDD' (20.01.2011, 00:04:04)
Import phase 'AUTO_MOD_SPDD' was already processed -> skip phase
Import phase 'RUN_SPDD_?' (20.01.2011, 00:04:04)
Import phase 'RUN_SPDD_?' was already processed -> skip phase
Import phase 'DDIC_ACTIVATION' (20.01.2011, 00:04:04)
Import phase 'DDIC_ACTIVATION' was already processed -> skip phase
Import phase 'IMPORT_PROPER' (20.01.2011, 00:04:04)
Import phase 'IMPORT_PROPER' was already processed -> skip phase
Import phase 'PREPARE_XPRA' (20.01.2011, 00:04:04)
Import phase 'PREPARE_XPRA' was already processed -> skip phase
Import phase 'AUTO_MOD_SPAU' (20.01.2011, 00:04:04)
Import phase 'AUTO_MOD_SPAU' was already processed -> skip phase
Import phase 'XPRA_EXECUTION' (20.01.2011, 00:04:04)
8O Abort the import due to an error situation (20.01.2011, 00:05:10)
Import of the current OCS Queue (20.01.2011, 15:41:16)
The import is done with the Standard scenario
The import is continued in phase 'XPRA_EXECUTION'
Import phase 'PROLOGUE' (20.01.2011, 15:41:27)
Import phase 'PROLOGUE' was successfully finished (20.01.2011, 15:41:28)
Import phase 'CHECK_REQUIREMENTS' (20.01.2011, 15:41:28)
Import phase 'CHECK_REQUIREMENTS' was successfully finished (20.01.2011, 15:41:29)
Import phase 'DISASSEMBLE' (20.01.2011, 15:41:29)
Import phase 'DISASSEMBLE' was already processed -> skip phase
Import phase 'ADD_TO_BUFFER' (20.01.2011, 15:41:29)
Import phase 'ADD_TO_BUFFER' was already processed -> skip phase
Import phase 'MODIFY_BUFFER' (20.01.2011, 15:41:29)
Import phase 'MODIFY_BUFFER' was already processed -> skip phase
Import phase 'IMPORT_OBJECT_LIST' (20.01.2011, 15:41:29)
Import phase 'IMPORT_OBJECT_LIST' was already processed -> skip phase
Import phase 'OBJECTS_LOCKED_?' (20.01.2011, 15:41:29)
Import phase 'OBJECTS_LOCKED_?' was already processed -> skip phase
Import phase 'TEST_IMPORT' (20.01.2011, 15:41:29)
Import phase 'TEST_IMPORT' was already processed -> skip phase
Import phase 'ADDON_CONFLICTS_?' (20.01.2011, 15:41:29)
Import phase 'ADDON_CONFLICTS_?' was already processed -> skip phase
Import phase 'SCHEDULE_RDDIMPDP' (20.01.2011, 15:41:29)
Import phase 'SCHEDULE_RDDIMPDP' was already processed -> skip phase
Import phase 'CREATE_VERS_BEFORE' (20.01.2011, 15:41:29)
Complete creation of version is switched off -> skip phase
Import phase 'SPDD_SPAU_CHECK' (20.01.2011, 15:41:29)
Import phase 'SPDD_SPAU_CHECK' was already processed -> skip phase
Import phase 'DDIC_IMPORT' (20.01.2011, 15:41:29)
Import phase 'DDIC_IMPORT' was already processed -> skip phase
Import phase 'AUTO_MOD_SPDD' (20.01.2011, 15:41:29)
Import phase 'AUTO_MOD_SPDD' was already processed -> skip phase
Import phase 'RUN_SPDD_?' (20.01.2011, 15:41:29)
Import phase 'RUN_SPDD_?' was already processed -> skip phase
Import phase 'DDIC_ACTIVATION' (20.01.2011, 15:41:29)
Import phase 'DDIC_ACTIVATION' was already processed -> skip phase
Import phase 'IMPORT_PROPER' (20.01.2011, 15:41:29)
Import phase 'IMPORT_PROPER' was already processed -> skip phase
Import phase 'PREPARE_XPRA' (20.01.2011, 15:41:29)
Import phase 'PREPARE_XPRA' was already processed -> skip phase
Import phase 'AUTO_MOD_SPAU' (20.01.2011, 15:41:29)
Import phase 'AUTO_MOD_SPAU' was already processed -> skip phase
Import phase 'XPRA_EXECUTION' (20.01.2011, 15:41:29)
Error during executing the tp command 'tp XPA ALL JBQ ...'
tp return code: '0008' , tp message: 'A tool used by tp produced errors' , tp output:
This is tp version 372.04.70 (release 700, unicode enabled)
Warning: Parameter DBLIBPATH is no longer used.
standard output from tp and from tools called by tp:
8O Details of the error situation can also be found in the import logs
Import of the current OCS Queue (20.01.2011, 16:13:18)
The import is done with the Standard scenario
The import is continued in phase 'XPRA_EXECUTION'
The current OCS Queue consists of:
001: SAPKIBIIQ4
002: SAPKIBIIQ5
003: SAPKIBIIQ6
Import phase 'PROLOGUE' (20.01.2011, 16:13:24)
Import phase 'PROLOGUE' was successfully finished (20.01.2011, 16:13:25)
Import phase 'CHECK_REQUIREMENTS' (20.01.2011, 16:13:25)
Import phase 'CHECK_REQUIREMENTS' was successfully finished (20.01.2011, 16:13:26)
Import phase 'DISASSEMBLE' (20.01.2011, 16:13:26)
Import phase 'DISASSEMBLE' was already processed -> skip phase
Import phase 'ADD_TO_BUFFER' (20.01.2011, 16:13:26)
Import phase 'ADD_TO_BUFFER' was already processed -> skip phase
Import phase 'MODIFY_BUFFER' (20.01.2011, 16:13:26)
Import phase 'MODIFY_BUFFER' was already processed -> skip phase
Import phase 'IMPORT_OBJECT_LIST' (20.01.2011, 16:13:26)
Import phase 'IMPORT_OBJECT_LIST' was already processed -> skip phase
Import phase 'OBJECTS_LOCKED_?' (20.01.2011, 16:13:26)
Import phase 'OBJECTS_LOCKED_?' was already processed -> skip phase
Import phase 'TEST_IMPORT' (20.01.2011, 16:13:26)
Import phase 'TEST_IMPORT' was already processed -> skip phase
Import phase 'ADDON_CONFLICTS_?' (20.01.2011, 16:13:26)
Import phase 'ADDON_CONFLICTS_?' was already processed -> skip phase
Import phase 'SCHEDULE_RDDIMPDP' (20.01.2011, 16:13:26)
Import phase 'SCHEDULE_RDDIMPDP' was already processed -> skip phase
Import phase 'CREATE_VERS_BEFORE' (20.01.2011, 16:13:26)
Complete creation of version is switched off -> skip phase
Import phase 'SPDD_SPAU_CHECK' (20.01.2011, 16:13:26)
Import phase 'SPDD_SPAU_CHECK' was already processed -> skip phase
Import phase 'DDIC_IMPORT' (20.01.2011, 16:13:26)
Import phase 'DDIC_IMPORT' was already processed -> skip phase
Import phase 'AUTO_MOD_SPDD' (20.01.2011, 16:13:26)
Import phase 'AUTO_MOD_SPDD' was already processed -> skip phase
Import phase 'RUN_SPDD_?' (20.01.2011, 16:13:26)
Import phase 'RUN_SPDD_?' was already processed -> skip phase
Import phase 'DDIC_ACTIVATION' (20.01.2011, 16:13:26)
Import phase 'DDIC_ACTIVATION' was already processed -> skip phase
Import phase 'IMPORT_PROPER' (20.01.2011, 16:13:26)
Import phase 'IMPORT_PROPER' was already processed -> skip phase
Import phase 'PREPARE_XPRA' (20.01.2011, 16:13:26)
Import phase 'PREPARE_XPRA' was already processed -> skip phase
Import phase 'AUTO_MOD_SPAU' (20.01.2011, 16:13:26)
Import phase 'AUTO_MOD_SPAU' was already processed -> skip phase
Import phase 'XPRA_EXECUTION' (20.01.2011, 16:13:26)
8O Error during executing the tp command 'tp XPA ALL JBQ ...'
8O tp return code: '0008' , tp message: 'A tool used by tp produced errors' , tp output:
This is tp version 372.04.70 (release 700, unicode enabled)
Warning: Parameter DBLIBPATH is no longer used.
standard output from tp and from tools called by tp:
8O Details of the error situation can also be found in the import logs
8R Interrupt the import due to an error situation (20.01.2011, 16:15:02)
Display detailed informations concerning the error in phase 'XPRA_EXECUTION'
8O Abort the import due to an error situation (20.01.2011, 16:23:10)
Sanjeev
>
> 8O Error during executing the tp command 'tp XPA ALL JBQ ...'
> 8O tp return code: '0008' , tp message: 'A tool used by tp produced errors' , tp output:
> This is tp version 372.04.70 (release 700, unicode enabled)
> Warning: Parameter DBLIBPATH is no longer used.
> standard output from tp and from tools called by tp:
> Sanjeev
Looks like a problem with the environment variable.
Kindly ceck DBLIBPATH at OS level.
Regards,
Nirmal.K
Dear Nirmal,
Before apply this patch i apply other patch and all patch working fine but when i stuck in BI_CONT.
and i was not able to delete the queue i reset the spam through se37.
one of my friend told me that after reset the spam not possible to resolve this issue.
we should restore the system can you help me i this issue because
i do not want to restore the whole system.
Sanjeev
Edited by: Sanjeev Mishra on Jan 25, 2011 6:31 AM
Hi,
Could you please paste the log of this phase ?
Thanks
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.