on 01-22-2011 7:06 AM
Hi Experts,
I have a peculiar issue with regard to work in the project builder. I have a scenario like there are different departments viz CIVIL,MECH etc. Different types activities are carried out at each department. For example, CIVIL has different activities like excavation, Reinforcement, shuttering etc. These activities have different unit of measures like m3 and m2.
I have created one work center CIVIL and activities as different activity types. I am using this work center for scheduling and cost planning.
In work center, I have defined as below
Capactites tab: capacity category 008, no formula to calculate capacity, base unit of measure is DAY
Scheduling tab: capacity category 008, other formula SAP004. No other selection
Costing: Cost center , activity type and formula SAP008
When I am creating new activity, I am giving details like work center, work (m3), duration and activity type. Now I could able to schedule and save the project. I checked the reports, the planned cost is also correct.
But when I am trying to change the planned work in the project by different quantity(not changing the unit of measure), getting error as u201CEnter the value for work in unit of timeu201D
Is this the standard behaviour or am I missing some thing
Regards,
Laxminarsimha
Hi,
Its a standard system.
If the UOM is different from one activity to another or in the activity, various activity element.
When u r confirming also, u wont get a progress as expected.
Regards,
N.Raju.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Laxminarasimha
Try to maintain Other formula - SAP008 in Capacity tab. currently you are not maintaining. Hope this will work.
Regards,
PSR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I am able to work with the same scenario.
Pls check the following points.
1. Work Center Cat / Usage : 0006 / 003
2. WC Capacity Tab - either 001 or 002 & formula "SAP008"
3. Capacity Header Details
Here try to maintain the Unit Conversions..... a) go to Extras -- UOM. b) enter the relation between your time unit & work units. c) then select UOM of your capacity (screen area right to Operating time field) as the work unit & press enter. System should display the relevant units of your work UOM in relation to the operating time. d) go back.
4. WC Scheduling Tab - For the same Capacity Category , a) dont enter any formula in Execution time (Other formula). b) Maintain Work Dimension as "MASS" from your F4 option & Maintain the Work Unit.
5. Save the workcenter.
6. Now try to create new activities / Network.
7. Set Calc Key to "Maintain Manually"
8. Enter Normal Duration & Work manually.
9. Save the network. Re Open & try to change either of the above values & save the network.
Hopefully this should ensure that the error doesnot come.
regards
Thank you so much for the detailed explanation
I have few doubts in step 3. We have work units as M3,MT and M2. Initially I have tried with M3. We dont have specific logic to convert work unit into time unit. But I gave relation as below
1000M3= 1DAY
I am maintaining my base unit of measure as DAY.
In Scheduling tab, I have maintained capacity category as 1(same as in capacity tab), But when I am trying to maintain work dimension as MASS and work unit as M3, system throws below error message
Unit M3 does not have dimension MASS
Message no. CR057
Regards,
Laxminarsimha
Hi,
Also maintain
1. your operating time unit in "HR" instead of "DAY" in Capacity Header tab.
2. In Extras -- UOM, maintain XX Hours = XX M3 (example 1 Hour = 10 M3)
2. Ensure that "M3" is entered in KAPEH field (field next to operating time in Standard Available Capacity subset of Capacity Header details screen.
3. System should then display the relevant M3 (for example if your operating time is 08 hours then automatically system should display 80 M3 against that.
regards
Hi,
I am checking for a new activity/network and also not maintaining formula SAP004 in Scheduling tab.
I am doing as below
WC masterdata:
Basic data tab: work center category 006 and usage 003
capacities: capacity category 001 and other formula SAP008
in capacity detailed tab: Base unit of measure DAY
in start availability capapcity: operating time 24, capacity 1000M3
in Unit of conversion 1000M3 = 1 DAY
in scheduling tab:capcity category as 001,
work dimension as VOLUME and work unit as M3
In Project:
I am assigning the above work center to an activity and in work field 1000M3 and calculation key as "Maintain manully" and saving the project. then when I re open the project and change the quantity from 1000 to other value, it is not allowing me to change.
Please let me know if I have missed out any step
Regards,
Laxminarsimha
Hi,
As per you suggestion, I have changed the Base unit of measure to HR
then maintainted the conversion relation 1000M3=24Hrs and "M3" is entered in KAPEH field.
I can see capacity as 1000M3(individual capapcity is 1).
Then tried the same in new activity/network but the error still occurs
Regards,
Laxminarsimha
Hi,
OK.
1.
In the Capacity HDR tab, there is a checkbox "Relevant to Finite Scheduling".
Dont activate that.
2.
In the Capacity Tab, try to display formula "SAP008". Check whether it is allowed for scheduling (check box "Allowed Sched."). By default it should be checked as I guess. Maintain "ZSAP008" & remove "Allowed for scheduling" checkbox.
regards
i dont think the error arise due to PS issue. i tried to search for the notes for your error message I got only this Note 1084040 - Incorrect error message when changing value for work. This note doesnt solve your problem, but it hints you that error message /MRSS/RAP059 belongs to software component MRSS. May be this component is integrated to your PS system(just my assumption) or could be a system bug which triggers this error message. so, the best way is raise an OSS message.
i dont think the error arise due to PS issue. i tried to search for the notes for your error message I got only this Note 1084040 - Incorrect error message when changing value for work. This note doesnt solve your problem, but it hints you that error message /MRSS/RAP059 belongs to software component MRSS. May be this component is integrated to your PS system(just my assumption) or could be a system bug which triggers this error message. so, the best way is raise an OSS message.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |