on 01-21-2011 2:29 PM
Dear PS SAP Gurus
Can you please advise if it is possible to display the annual actual / plan costs for WBS Elements in the stucture overview reports CN41 and CN41N. I can only get cumulative values.
Many thanks
PRG
In CN41N or CN41 click/select the WBSE, then Goto>Periodic breakdown, here you can see the cost details per period and fiscal year.