Hi All,
I have a material A with 04 inspection type (Goods receipt from production) activated. I have quantitative MIC XYZ with min & max specs maintained as 10 to 15 in MIC.
I have two inspection plans for material no - 1 & 2. In plan no 1 MIC XYZ is having specs as 11 to 13 & in plan no 2 MIC XYZ is having specs as 12 to 14.
While doing GR of material A through production order, system will generate inspection lot. I want I could assign the desired inspection plan to be assigned to that inspection plan & then carry out result recording according.
How this can be done?
Regards,
MHP
In the header of the plans, click on material assignment button on the button bar. In the next pop up screen, enter in the material number and plant to be assigned to the group counter.
If you assign each material to only one plan, the plan will be automatically assigned. If you have more than one plan assigned, you can go to QA02 to pick from the assigned plans. If you have some way of knowing which plan of the many is to be assigned, you can maybe use the user exit mentioned to assign the right one.
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Precisely you can use
User Exit
QPAP0002 Enhancement for material/plan assignment, plan selection
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.