We are on cProjects-RPM 4.5. We have the accounting system/PS along with CPR-RPM in the same system.
This is how we have set the integration:
- create RPM item. This creates the cProjects Project automatically
- setting the cProjects Project to "Flag for transfer" creates the PS Project
From here on, we need to carry fruther with the following:
- We intend to post costs and revenues (both planned and actual to the WBS elements in PS)
- We intend to bring these costs (and revenues) under appropriate financial views in RPM, under Financial Planning
Please advise.
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi chand
we have the same scenario about integration RPM to cProject,cProject to PS project。
I have finished the configuration:
- create RPM item. This creates the cProjects Project automatically, such as item "RPMA",and cProject project "CPRA"
- setting the cProjects Project to "Flag for transfer" creates the PS Project, such as "PSA"
but I don't know how to finished this step:
- We intend to bring these costs (and revenues) under appropriate financial views in RPM, under Financial Planning.
i think the PS project "PSA "maybe as the object link about item "RPMA", and the object link should be created automatically.
could you give me some suggestion?
thanks
Jessie
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.