cancel
Showing results for 
Search instead for 
Did you mean: 

V_V2 is not considering the customer stock to reschdule the sales order

Former Member
0 Kudos

Hi,

Here is my scenario:

-Created a sales order and linked the Purchase order to that.

-PO delivery date is in the future say for example 4/20/2011.

-Sales order schedule line date is updated based on the PO delivery date.

-But goods are received far earlier than the PO delivery date. say 1/28/2011.

-When the goods are received "Customer stock" is updated, but not the "Availability stock" .

-When i run the back order rescheduling using V_V2 the sales order is not updated. Even though Goods are received for tha PO against that sales order(since the stock is Cstock not "available stock".

- Eventually Sales order cannot be delivered even though stock is there in the warehouse as "Customer stock".

Really appreciate if anyone could provide ideas to resolve the issue to deliver the sales order as soon as goods are received into the warehouse against the PO which is linked to that sales order.

Thanks,

sre

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

Pl verify ATP control parameter and also your checking group in material master.

thx

Dilip Sadh