on 01-19-2011 2:51 PM
Hi,
I'm trying to transfer a multilevel Bill of Materials (BOM) to a project using CN33 transaction but I'm only getting fist BOM level transferred.
This is the way I'm doing it:
I create a BOM (BOM usage 1) with two items. Then I add this BOM as an item in an other BOM (with same BOM usage). All the items, of both BOMs, have the same reference point.
Then, from TCode CN33, I click on selection parameters to set: Multilevel, Preliminary reqmts and All Items on the General tab, on the Constraints tab i put a 5 on explosion level (I guess that with a 2 it would be enough).
I select the project definition, the material (main BOM), the plant, the bom usage and alternative but on the Result Overview I only see the items of the higher bom, it's not getting the items of the second one.
What I'm missing?
Thanks a lot
Check procurement key in MRP-2 view of Level 1 BOM materials, it must be E & not F. Also check the validity dates on the BOM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.