Hi,

I'm trying to transfer a multilevel Bill of Materials (BOM) to a project using CN33 transaction but I'm only getting fist BOM level transferred.

This is the way I'm doing it:

I create a BOM (BOM usage 1) with two items. Then I add this BOM as an item in an other BOM (with same BOM usage). All the items, of both BOMs, have the same reference point.

Then, from TCode CN33, I click on selection parameters to set: Multilevel, Preliminary reqmts and All Items on the General tab, on the Constraints tab i put a 5 on explosion level (I guess that with a 2 it would be enough).

I select the project definition, the material (main BOM), the plant, the bom usage and alternative but on the Result Overview I only see the items of the higher bom, it's not getting the items of the second one.

What I'm missing?

Thanks a lot

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check procurement key in MRP-2 view of Level 1 BOM materials, it must be E & not F. Also check the validity dates on the BOM.

fortian
Active Contributor
0 Kudos

The issue was in the procurement key.

Thanks

Answers (0)