redetermined the past due schedul lines in Scheduling agreement

lakshmikanthc2
Active Participant
0 Kudos

Hi All,

We have an issue with past due schedule lines in scheduling agreement, the details are below.

Delivery date: 3rd Jan 2011 - Order qty is 100 no confirmtion. The system has proposed new date that is 19.01.2010 (System date) with full confirmation. The Scheduling agreement is not relevant for ATP check also. When we check with other plant scheduling agreement, it is not determining any new date, it is confirming on same date.

Different Document types used in two cases, but the config is same in both cases. Not sure why the system is determining to current date with full confirmation. Is there any config relevant to this.

Regards,

Lakshmikanth

Accepted Solutions (0)

Answers (3)

Answers (3)

lakshmikanthc2
Active Participant
0 Kudos

Hi All,

Found the issue, the document type is marked as forward shceduling, that's why it is proposing new date for past due schedule lines. If it is backward scheduling, the past due schedule lines are also getting confirmed on same date.

Thanks for your replies.

Regards,

Lakshmikanth

Lakshmipathi
Active Contributor
0 Kudos

As you should be aware, stock in sales documents will get confirmed based on certain parameters. They are

1) scheduline category configuration

2) GR Processing/In-House data in material master

3) Pick/Pack time from your shipping point

4) Lead time maintained to your scheduling agreement in VOV8

So have a look in the above areas for both the document types.

thanks

G. Lakshmipathi

Former Member
0 Kudos

hi

schedule lines in scheduling agreements = correct & confirmed dates.

that means if you enter the date manually here system confirms that date as schedule line date.

compare those two plants and let me know if any difference is there in between.

check MMR RLT's MRP views

check Lead time in days - document types

check & confirm.

balajia