Hi Friends,

I am facing following error

No expenditure items found Message no. VPK1310

Steps done

Created inquiry and assigned DIP profile in Sales B and WBS also assigned.

In CJI3, i found 50,000 - for a cost element 400000 for this WBS element

But in DP81 i am receiving the above error.

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Check these notes. Might be helpful.

Note 940270 - DP80: Error message VPK1 310 even though costs exist

Note 1094018 - DP90: Error message VPK1 310 even though costs exist

Note 1130699 - DP90 and message "No expenditure items found"

Regards,

Gokul Pillai

Edited by: Gokul Pillai on Jan 19, 2011 11:26 AM

virendra_pal
Active Contributor
0 Kudos

You have no plan costs

Please search for similar threads in the forum before posting

former_member494495
Active Contributor
0 Kudos

Hi Virendra,

I maintained in CJ40 and also in CJI3 i found actual costs.

Could you please elaborate how i can maintain the plan costs ?

Thanks.

former_member494495
Active Contributor
0 Kudos

I checked already in forum berfore posting but i couldn't solve this.

Please send some documents for Sales pricing

Former Member
0 Kudos

If you are trying to generate a Sales price basis, What is your Source in DIP profile.

Also I dont think planning in CJ40 will update your cost elements, if you are using cost elemnts as charcteristic.That is why it was mentioned in the previous thread that

You have no plan costs

But you have mentioned you are able to see in CJI3 actual cost against a particular cost elemnt, in that case Is you actual cost is acting as a basis for your sales pricing? Generally when you are preparing a quotation you estimate and plan the cost to create a sales price basis.

Kindly ellaborate....

former_member494495
Active Contributor
0 Kudos

HI,

I maintained Activity type, cost center, costelement in source profile.

I changed to planned costs -total records

Now what should i do to have a plan costs ?

Thanks

Edited by: Virendra Pal on Jan 19, 2011 4:54 PM

This thread is now locked and all points unassigned

Please read SAP help or do some course or ask your PS consultant - do not expect us to configure your system for you.