Hi experts,
I am preparing a prototye for my customer. It is an end-to-end (forecast-SNP-PPDS).
What I have done yet:
- Calculated forecast
- run SNP heueristic for multi level planning. --> SNP production order are created
The issue I am currently facing now is: I created a lot of SNP planned orders in production plant but capacity consumption is still zero. Any idea what else I should do?
Thanks
Aban
Hi,
Where are you checking for the resource consumption for these planned orders.
After running heuristic you can use the planning book 9ASNP94 with data view SNP94(2) to level the capacity.
First check whether there is any capacity overload is there for the resources and then do the cap levelling.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Handha,
Thanks for reply.
What I did:
- I put big amount of quantities on certain periods to generate capacity overlaod.
- I run heueristic by using SNP view SNP94(1)
- After I started SNP94(2) to check capacity situation.
What I am wondering at is: there is no capacity consumption in an of the resouces which are used for this product in a specific location (production plant for this product).
For your info: PDS has been transfered and capacity are flagged as Multi Mix in ECC system
Thank you for your support
Aban
Could you please check if the operations/orders are dispatched on the resources. It should not be deallocated on the resources.
Rgs - Vikas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.