Fixed Cost & Variable cost in Production Order

Former Member
0 Kudos

Hi ,

I have maintained the fixed cost & Variable cost in KP 26 for the activity type .

for 1 hr

Fixed cost : 1

Variable cost :1

Operation duration is 1 hr , when i check the Planned cost it shows total plan cost is 6.92 ,

Fixed cost as 3.46 and variable cost as 3.46 ,

How the system calculates 6.82 ,

I have maintained the valuation Variant for the activity type is Plan price for the period .

As per my understanding system has to calculate the Planned cost as 2 (1 for fixed + 1 for Variable )

Can anybody explain me why the system calculated the price as 6.82 ...

Thanks in Advance ...

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member196530
Active Contributor
0 Kudos

Dear,

Please check the following :

1.Goto CR02-Slect the Costing tab -Check the Formula Key assinged in the Work Centre costing tab .??

2.Please note that variable cost is dependant on quantity, where as fixed cost is independent of quantity.

For example, if you have updated Rs.300 in variable and Rs.200 in Fixed cost fields and you quanity of activity type consumed is 100 minutes.Your fixed cost will be Rs.200 and variable cost will Rs.300/minute * 100 = Rs.30000

3.What s the currency in Controlling area ??

Regards

JH

Former Member
0 Kudos

Hi,

Please check the overhead costs calculation and revert.

Regards

Chandra

Former Member
0 Kudos

- Check the formulas in the work center (resource)

- Check the currency in your Controlling Area

- How do you test the costs ? In the work center ? Or do you create an order ?