cancel
Showing results for 
Search instead for 
Did you mean: 

MRP Indicator

Former Member
0 Kudos

Hi All,

This is regarding the MRP indicator for excluding the SLOC from MRP run.

We have the configuration settings in OMIR for the SLOC to be excluded from MRP run. If we maintain the MRP indicator as "1" for the SLOC in the configuration, it will exclude the SLOC from MRP run.

Also we have one more setting for MRP indicator in the Material Master. When we here maintain the MRP indicator in the SLOC, it will exclude the SLOC from MRP run for the material.

But which setting has the high priority? whether setting in configuration or setting in Material master?

Also we maintain the indicator in the configuration, the available stock in the MD04 includes the all the SLOC stock which has the indicator also. But we maintain the indicator in the material master, the stock is showing separately for SLOC which is excluded.

Kindly explain.

Regards,

Sureshbabu G.

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

Hi Suresh,

First of all the basic concept/process behind using this is as follows below.

Material requirements planning with MRP areas cannot be reversed once activated. During conversion i, SAP will automatically create a MRP area for all your existing Plants. Now, you can start creating the MRP area for storage location or vendor to be planned separately. That's is the whole purpose for using MRP area. Here you define whether the MRP area type :- 01 - Plant 02 - Storage Location 03 - Vendor . In Material Master MRP 1, the MPR area section will appear once you successfully complete the above Steps. Assign MRP Areas to Materials You assign the MRP areas to the materials by creating an MRP area segment for each MRP area in the material master. You can assign several MRP areas to one material. MRP with MRP areas for the material is not activated until an MRP area has been assigned to a material. If you have not assigned an MRP area to a material, that is, you have not created an MRP area segment in the material master, the material will continue to be planned in the plant MRP area only. If you have assigned an MRP area to the material, the system can plan it in the plant MRP area and in the assigned MRP area. You can display an overview for all materials in an MRP area. To do this, you go into Customizing for MRP and choose the IMG activity Define MRP areas. Call up an MRP area by double-clicking and choose Material overview for MRP area. Check Storage Locations If you have already entered a storage location in the BOM (BOM item), in the work center (supply area) or in the production version, you should check whether this storage location is the storage location for the MRP area that you have assigned in the material master. The materials are assigned to an MRP area via the storage location that the system determines during the planning run. You should therefore check the storage locations that you have maintained in the material master. The storage location in the material master must be a storage location for the MRP area, for which you have created an MRP area segment in the material master. You can therefore ensure that material requirements planning will be carried out for the correct MRP area The MRP area represents an organizational unit for which material requirements planning is carried out independently. Basically, there are three types of MRP area: Plant MRP Area The plant MRP area initially contains the plant together with all its storage locations and stock with subcontractors. When you have defined MRP areas for storage locations and for subcontractors and you have assigned the materials, the plant MRP area is reduced by exactly this number of subcontractors and storage locations. This is because they are now to be planned separately. MRP Areas for Storage Locations You can define an MRP area that consists of a particular storage location, by creating an MRP area and assigning the storage location to it. Material requirements for this storage location are then planned separately from the rest of the plant. You can also group several storage locations into one MRP area, by creating an MRP area and assigning the storage locations to it. These storage locations are then planned together. A storage location of a plant may be assigned to only one MRP area. MRP Areas for Subcontractors You can also define an MRP area for each subcontractor. A subcontractor may be assigned to only one MRP area.

MRP areas of the storage location or subcontractor type are only suitable for: 1. components that are planned and produced for stock 2. finished products that are planned and produced for stock. By assigning a storage location in a sales order or by entering an MRP area when creating the planned independent requirements, you can define whether a material is planned in the plant MRP area or in the MRP area of the storage location. Material requirements planning for each MRP area allows you to have specific control over the staging and procurement of parts produced in-house and purchased parts for each shop floor and assembly area. If, for example, you define an MRP area for the production storage location of an assembly line, the system plans the material requirements for the assembly line separately from all other requirements. Example: Subcontractor You can also carry out planning for components to be provided in subcontracting using an MRP area by defining an MRP area for every subcontractor and assigning the components to be provided to the MRP area of the subcontractor. You therefore plan the requirements to be provided for these components for one subcontractor separately from all other requirements. Depending on the requirements situation, the system creates either stock transfer reservations from the plant to the stock of material provided of the subcontractor or it creates purchase requisitions within subcontracting/third-party order processing, according to the special procurement key settings.

hope this would be useful for you at some extent.

please revert if required.

Regards

Chandra

Edited by: Saraswati chandra on Jan 18, 2011 11:33 AM

Former Member
0 Kudos

Ancient Egypt specialist in Cryptography required !!

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

The settings made in Customizing transaction OMIR are only default values for the creation of the material master.They have no effect on the actual planning of a storage location.Only the settings for the storage locations in the respective material masters are important for materials planning.Refer to note 386491 for additional information on that point.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Settign in OMIR is used to default the MRP indicator defines while extending the mrp views to storage location level or in MMSC.

However you can change the same in Material master or MMSC nad this is the one which is considered in MRP. Settings from OMIR alone are not considered but used for defaulting values only.

former_member533946
Active Contributor
0 Kudos

Hi dear,

System will first follow the settigns done in OMIR and then in material master.

former_member467138
Active Contributor
0 Kudos

Hi,

No higher priority in both settingsu2026 both r same OMIR settings are done by plant level

Then comes MMSC or in material master MRP View done by material level.

Arun

Anupam1143
Active Contributor
0 Kudos

HI

For a material bot setting from OMIR and MMSC or Material master > MRP indicator 1 is required in order to exclude from MRP.

Check and revert

Regards

Anupam Sharma

Former Member
0 Kudos

hi

the setting in the mat master will take hiher priority.The setting in config is at the plant level

Amit