on 01-17-2011 5:45 AM
Dear QM Master,
Good Day,
Currently i encounter one Problem found as below :
We have 2 plant , plant 1000 & plant 2000.
Classification class is created as RM_Additives by plant 2000.
QA department would like to create characteristic Assignment (QS61), default plant set as 2000.
Therefore, QA cannot create inspection items for plant 1000.
Consequently, QA cannot proceed for UD or release (QA32).
Please advise.
Thank you.
How can characteristic Assignment (QS61) default plant set as 2000 but QA still can create inspection items for plant 1000 ?
This is my question.
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
But after when i going into Change Inspection Lot screen, it will appear the error message "NO physical samples are assigned"
so i can't change the inspection lot , so cannot release UD and cnanot GR because cannot UD until now.
Please advise what's the error messaage "No sample are assigned "
Thank you.
I am not very sure what exactly you want to acheive but
If your ultimate aim is to not allow UD by other plant then You can use User exit
QEVA0010 |UD: Usage decision check
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
10 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.