cancel
Showing results for 
Search instead for 
Did you mean: 

Activity element confirmation- Budget availability

Former Member
0 Kudos

Hi all

In network costing I have created internal activity elements under an internal activity. This is because the activity has to be performed in more than one work centre. The activity therefore includes only duration and the activity elements has work, work centre and actvity type mapped in them. The planned cost for activity elements are displayed correctly.

Referring to report S_ALR_87013558, when I confirm the activity element, the actuals column is correctly updated. The problem is that, the"Remordplan" column that should be ideally reduced by the amount of actual value shows no change and because of this the values in the assigned colum exceeds the available budget.

Request to please throw some light on this, if anybody has had the same issue in the past.

Thanks

Pradeesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Still wating for the reply. The issue still remains

Former Member
0 Kudos

Try reconstructing both project info database(CJEN) & Availability control Info(CJBN).

Former Member
0 Kudos

Hi

Thanks for the reply. I have tried this, but still the problem remains.

Please suggest.