Dear APO Expert,

I work with new Master data Created , Product and Location

PP Planning Procedure : IDES: Automatic planning immediately

I create new demand for Product P-100 at Distribution Center 2013

Production Plant at 2011

when i transfer Demand whether through /SAPAPO/MC90 or Mass Processing , I can't find any Order's created for this plan at 2011 or even PurRqs at 2013

Please Advise

Rami

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Can system determine appropriate product heuristics to be used.

For checking:

You may try if possible, to update the field "Product heuristic" with a value e.g. SAP_PP_002 on the tab "Planning Procedure" in

PPDS tab of the product master.

Regards

Datta