Dear APO Expert,
I work with new Master data Created , Product and Location
PP Planning Procedure : IDES: Automatic planning immediately
I create new demand for Product P-100 at Distribution Center 2013
Production Plant at 2011
when i transfer Demand whether through /SAPAPO/MC90 or Mass Processing , I can't find any Order's created for this plan at 2011 or even PurRqs at 2013
Please Advise
Rami
Hi,
Can system determine appropriate product heuristics to be used.
For checking:
You may try if possible, to update the field "Product heuristic" with a value e.g. SAP_PP_002 on the tab "Planning Procedure" in
PPDS tab of the product master.
Regards
Datta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.