Hi Experts
I am looking at whether during the settlement rule creation process via CJB1/CJB2 can be prevented from overriding the Results Analysis key on the WBS element with what ever is held at the Project level.
While creating the settlement rule directly in CJ20N this does not happen.
Is this std SAP which can be deactivated?
Thank you in advance
Check the setup of 'Determine strategy for settlement rule' for the strategy used. In that definition there would be a different RA key as compared to the one which is in your project initially & this would be causing a change.