cancel
Showing results for 
Search instead for 
Did you mean: 

Experience transferring PS Networks into APO

Former Member
0 Kudos

Just wondering if anyone out there has experience transferring PS networks into APO? I've done a few tests but I've been receiving a few errors including:

"Invalid I/O node configuration"

"Cannot determine scheduling parameters for network 000004000082"

"No transfer of relationship between activity 000004000082 / 0030 and activity 000004000083 / 0010"

Also - When these do transfer through to SCM - where should I be looking to verify?

Thanks in advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

m_manimaran
Active Contributor
0 Kudos

Hi,

For your second question, "When these do transfer through to SCM - where should I be looking to verify?

" - you can check your network order in the transaction /SAPAPO/RRP2. Select the radio button 'Project Order' and enter your 'Network order' number to view the project details.

Regarding your error messages,

Please check the procurement types of your components in the activities. This may be the reason for the first error.

Please check that the resources attached to the activities are transferred. and you have planning related details are entered in activities like duration.

Also, please view the graphical display of the network and see all the activities have relationship?

Please revert with your observations.

Regards,

Manimaran M.

wilian_segatto
Employee
Employee
0 Kudos

Hi!

Check this note:

Note 1114989 - Invalid I/O node configuration, scheduling in APO

Will