Dear all,

i have some fabricated matreial with value

its not taken in the cut over stage to stores

now iwant to upload the stock through wbs element

and then want to do STO to a different palnt with excise invoice challan

please suggest the procedure

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member604117
Participant
0 Kudos

thanks

Former Member
0 Kudos

John,

I request you to provide a proper subject line for your threads.

virendra_pal
Active Contributor
0 Kudos

Ravi

Very good observation - do you have any suggestion - I will change it

Virendra

Edited by: Virendra Pal on Jan 13, 2011 10:13 AM

Subject changed from "User ID" to "Missed Intial stock upload"

Former Member
0 Kudos

Thanks,

I would have subjected as "Missed Intial stock upload."

Former Member
0 Kudos

Hi,

Go to MB1C & use 561Q movement type to uploade.

I haven't use this movement type..

Try this let us know helpfulness....

Hi Experts,

Open for your comments on uploading initial projects stockes using 561Q movement type.

Thanks & regards,

Sam L.

Former Member
0 Kudos

Yes the movement type is 561Q for intial project stock upload through MB1C.