Hello Gurus,

We know that when rescheduling is activated for a delivery document type, when creating a DO, and when goods are not available at the Material Availability date, a Forward scheduling will be carried out.

I like to confirm that the new material availability date need not be the Order Date = current date. It can be but need not be depending when there is availability.

regards

M Russo

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi;

exactly you are correct because when forward scheduling is carried by the system & these two dates is not necessarily IDENTICAL to each other. when forward scheduling is conducted by the system the dates will be given as near future availability date.

hope this clears your issue

regards

Answers (1)

Answers (1)

Shiva_Ram
Active Contributor
0 Kudos

I like to confirm that the new material availability date need not be the Order Date = current date. It can be but need not be depending when there is availability

Yes, this is correct.