on 01-10-2011 2:43 PM
Hi
We are implementing SRM7.0 with classic scenario and backbend ECC-Ehp4.
When we are trying to trigger creating of PO from SOCO the PO successfully created in the backbend is mapped with standard pricing procedure RM0000. If the mapping is for "Z" pricing procedure the PO creation fails with error "Net price must be greater than 0"(error seen in /sappo/ppo2 in ECC).
As we are very tight on enhancements is there any configuration where we can map the pricing procedure between ECC and SRM or is the only way to enhance the system.
with regards
Manjunath
Edited by: Manjunath Somashekara on Jan 11, 2011 12:57 PM
Edited by: Manjunath Somashekara on Jan 11, 2011 12:57 PM
Hi Manjunatha,
Are you using PB00, PBXX and PRS condition types in your z-pricing procedure ?
Best regards,
Ramki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Muthu,
PBXX condition type has the Condition class B and Category H, Z pricing procedure has been copied from RM0000 for maintaining some Z condition types.
In ME21N PO is successfully created with Z pricing procedure, issue is when we are trying to create PO from SRM it is failing.
with regards
Manjunath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.