on 01-10-2011 6:39 AM
Hi,
When I try to create a Network and put the start date I get an error message-
Date 01.01.2011 is later than the validity period of the factory calendar
Message no. CO032
Procedure
Enter a date which lies within the validity period of the factory calendar.
And this does not allow me to cfreate the network.
But the same date is accepted by the system for WBS element and activities.So I doubt it has anything to do with the factory calendar.
Please assist.
Thanks and Regards
Hi,
Goto SCAL transaction and check the validity period of the factory calendar. Extend the validity and then try.
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The validity end-period has been maintained as 2011 for the calandar.
One difference I noticed is that for activity and WBS element the calendar maintained is 01.While for network header we do not have any explicit factory calendar concept but I think the system derives the Factory Calendar from the assigned Plant.But even in the Plant the Factory Calendar maintained has the validity end-period as 2011.
In the network header's Basic Start field when I hit F4,then all the 2011 dates show in Italics-like the non-working SAT and SUN days.
Thanks and Regards