Hi all,
My requirement is order need to be scheduled on all alternate resource... and also it will adhere product sequence...
I have given cost as follows in optimization profile..
Make span=100
Setup cost=60
Mode cost=25
Cost and time i have maintained in setup matrix.
In the cost tab of optimization profile i have given A=10,B=100 as variable and 100,200 in fixed column..
Product sequence is some how adhering..but order is not going to alternate resource....
Thanks
pardeepta
HI Pradeepta,
1. Plz reduce the make span from 100 to 5 or make it NILL.
2. Make the mode cost as A=10, B =20, C=30 and so on
As you are doing optimization for a specified period to deliver the product to the customer, no need to give priority for u201CMAKE SPANu201D
Plz try with the above changes.
Thanks
Sravan Maturu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pradeepta,
I Believe, that might be u r observation.
To achieve the required scenario which you have given, plz follow the below steps
1. Plz check whether u have defined mode priority in PDS or not. If not plz define.
2. After maintaining do new explosion of transaction data
3. Plz maintain the weights in basic settings of optimization profile as "make span = 0", Total setup time = 50, Total mode cost = 70,
4. In Cost tab maintain fixed mode cost as A = 10, B = 12, C = 14 etc (In multiples of 2)
When you try this example ensure that u have 1 and half day load & give scheduling horizon as 1 day while optimization for the resources A, B & C.
System will schedule on Primary resource A first then it willl schedule on alternate resource B. If resource B is also full then only it schedule on resource C.
Note: If you define make span, then system will thing that you want to produce ASAP and results will be accordingly. make span has no relation with mode priority.
Regards
Sravan Maturu
Pradeep,
Not sure if you are working with PPDS or SNP for production Planning. In PPDS alternate PDS/PPM selection won't happen even if you have maintained priorities (exception repetitive manufacturing)
If you are trying to select alternate resource based on capacity constraints in PPDS you need to use modes.
Regards
Amlan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.