on 01-06-2011 1:40 PM
Hi Friends,
In all my sales order I want to make requested delivery date to the same day as the order is made. currently it is giving the next day.
For example if I make order on 06/01/2011 then system should give requested delivery date as 06/01/2011.
how can I achieve this.
Regards,
Wasim.
Go to VOV8, select your order type and execute. There tick the box for "Propose Delivery Date".
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lakshmi,
The tick for propose delivery date is there for all the document type. This problem was not there till yesterday, but since today it has started.
It is not happening for ane particular company code. its happening for all 7 company code defined in the system.
What could be the problem and the possible solution.
Regards,
Wasim.
Hi,
While you create a Sales order system automatically determines the material availability date using Scheduling process and can be seen in Schedule lines data. The Scheduling process uses the lead times defined in Shipping point and Route. If all the lead times - pick/pack time, loading time, transit time and transportation planning time are zero, the material availability date would be confirmed on the same day.....of course depending on the material availaibilty.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.