on 01-06-2011 4:35 AM
Hi Guru's,
Can we change the Materail quantity in billing when derliverya dn PGI as was compleated.
pelase revert back to me.
Ragards,
Rahim
Hi Rahim,
Kindly confirm the scenario
Delivery Doc.1 contains:
Item No...............Material.................Qty
10--
20--
Now, while Billing this Delivery Doc.1;
you want to change Quanties for Material ABC (from 20 to 10)
and for Material XYZ (from 30 to 15)
If this is the case. then, this is not possible with Standard-SAP
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Actual senarios is The order is made for 1000kg and when it goes to delivery they haev done enhancement with Weighbridge with sap, that is deducting Tare weight from the gross weight so the net weight is less than the ordered weight i.e 990.
But when it goes to billing it is caluclating on the 1000 of the ordered quantity.
that is making problem.
pelase help us in this regard.
Regards,
rahim
You are not clear on what you wan't ti bill.
The quantity delivered (removed from inventory) SHOULD have the tare weight on the container deducted.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In item category maintain billing relevance - K -Delivery-related invoices for partial quantity.
In billing oyu can change quantity manually.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rahim,
I will suggest to go for the proof of delivery functionality so that you can correct the delivered quantity and do the billing for correct quantity.
Changing the billing relevance to K at item category level will not be useful as balance quantity will be invoiced in next run or delivery will be due for invoicing for balance quantity.
Hope this will help you.
Please revert back to the forum in case of any concern.
Thanks and Regards,
Atul
Hi Atul,
The actual senario is due to weigh bridge application the Tare weight is getting deducted from the net weight i.e for 1000 qty order is placed and the delivered qty is 990, when it goes to billing it is taking 1000 only insted of 990.
This is what is the problem what we are facing here.
Reagads,
Rahim
Hi Rahim
Please go through the below link for additional information on POD
http://help.sap.com/saphelp_46c/helpdata/en/38/c1853488601e33e10000009b38f83b/frameset.htm
I will still suggest to adopt POD functionality.
Hope this will help you to resolve your issue.
Please revert back to the forum in case of any question.
Thanks and Regards,
Atul
hi
its not possible in standard sap for change of quantity.
but if you want split the billing for delivery line item quantity setting requried in itemcategory billing relevence as 'K'
Regards,
Nar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.