on 01-06-2011 3:07 AM
Hi all,
We are on SRM 7 , ECS scenario.
We have single SC type but have created different PO types in SRM , and used BADI to convert SC to different PO type , like consumable PO, service PO, etc, based on some logic.
Now we want all the requisitioners to do the SRM confirmation only for service PO , not for consumable PO , and other PO. How can we achive this ?
Rgds
Sumendra
Hi,
Use the importing parameter e_header of BBP_DOC_CHECK_BADI to identify what type of PO is created.
Regards,
Saixis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sumendra,
This can be easy.
Pl implement BBP_DOC_CHECK_BADI, where you can throw an error if user selects PO from any other PO type.
Best regards,
Ramki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.