PLANNING CALENDER IN LOT SIZE

former_member1013
Participant
0 Kudos

Hi

What is the function of Planning Calender in Lot Sizing procedure in SNP.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sanjay,

Planning calendar is used in Period lot sixing procedures. APO standard time stream is used as a planning calendar.

However, please note that planning calendar field value in Location product master- Lot size Procedure Tab is NOT taken into account in Supply Network Planning (SNP).

Regards

Datta

former_member1013
Participant
0 Kudos

Hi Datta,

Thanks for your reply.

But still I have many questions in this.Like...

1. If some of my locations are able to Deploy once in week,how do i make use of Period Lot size procedure.

2. And also let me know if Planning calender tab is not used at the time of Period Lot Size procedure which calender it follows if it makes to use the calender??

digambar_narkhede
Contributor
0 Kudos

As per standard SAP F1 help of field 'Planning calendar' it says "This field is not taken into account in Supply Network Planning (SNP)."

Regards,

Digambar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

You can define the planning calendar to define the periodicity of lot size.

For example in our case we want to SNP to create requirement only in alternate month based on lot size.

So we create planning calendar which consist only alternate month and attach to lot size.

Now when we execute the SNP planning, it will create supply element only in alternate month.

I hope this will give insight of it. Please let us know , if it helps you.

Thanks

Amol