Hi Experts,

Is there anyway for mass updating the operation details of production order.I want update maximum wait time and minimum wait time of each operation.

Please guide me the way to achive this.

Edited by: sam_ins123524 on Jan 5, 2011 5:23 PM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Sam,

First question is whether you are trying in ECC or SCM system?

SCM system procedure:

Plz check whether the MIn & Max wait times for the operations are available in PPM/PDS,

If the same is not available plz maintain the same. Once you maintain the data correctly then go to

/N/SAPAPO/CDPSB0 (Production planning Run)- use the heuristics 'NEW EXPLOSION' which will make changes for all the transaction data.

Thanks