When are running delivery due List, there are few sales orders remaining even delivery creation is done for all the sales orders.
Reason for that is sales has got confirmed through V_V2 Transaction i e sales order allocation. but actually there is no stock of that material. but how it is getting confirmed. what may be the reason?
Pls help
thanks in Advance
hi
Regarding this issue ,system is checking available of material on that day or system is calculating the procurement of
raw material & production of FG material
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check the stocks on THOSE DATES of order confirmation in MB5B.
It should be availble.
Pls check & revert
Sumanth.Gururaj
Consultant/Systems Analyst - SAP SD/MM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Confirmation of delivery date and availability of stock are two different things. A line item si confirmed doesnt mean that the stock will be available on that day.
When the delivery date is calculated, the future inflow and outflow of the materials are considered and thus the delivery date is arrived. So also during rescheduling. However after that some of the expected inflows would not have come and as a result, stock may not be available. This is the reason why the deliveries are not created for these materials.
May be you have to check the stock once and then update the stock before running the delivery job.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.