on 01-04-2011 2:03 PM
Dear Friends,
I am using SAP R/3 4.7 version, actually till 30th December there was no problem in delivery but form 1st Jan when I am creating any delivery against any order, it is showing the following error :-***
No schedule lines due for delivery up to the selected date
Message no. VL248
Diagnosis
There are no schedule lines due for the given order item up to the date chosen.
System Response
The system does not create a delivery item for this order item.
Procedure
Check whether the order item to be delivered contains confirmed schedule lines.
If this is the case, set the selection date further into the future if you still want to create a delivery for this item
Hi,
1. Please check the factory calendar. When is the calendar valid to?
2. Please check schedule lines in SO. What's the material available date in schedule line? Use that date to select.
Regards,
harry
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Harry! But problem is still there.
I want to tell you that I am using Factory Calender Germany Standard.
When I am doing stock posting through mb1c, I am getting the following error and I am not getting the way to fix this so if you can fix it I will be highly obliged:
Error is following when doing stock posting for any material:
Number range for trans./event type WA in year 2011 does not exist
Message no. M7562
Diagnosis
The number range for document number assignment has not been maintained in the year 2011 for the transaction/event type WA.
Procedure
Contact your system administrator.
If you are authorized to do so, do you want to check the number ranges for the
u2022 Material documents
u2022 Reservations?
If the material is a batch managed material, the batch you are assigning in the SO might have been reserved against some other sale order. (Check vbap table).
If the material is not a batch managed material the quantity which is apparently available might have been reserved against some sale orders created earlier.
Please check it up.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Singh
Use T . Code u2013 OMBT, then go to change interval , then go to edit > insert year (f6) and mention in year 9999 and choose the number range interval from number to number and mention in current number is 0 and save exit.
i think by your problme is solve .
Thanks & Regards
Niraj Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am looking for the relevant answer!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If anybody get the solution of this above problem please let me know about it !
Regards
Gaurav Kumar Singh
Edited by: singh_mba123 on Jan 5, 2011 6:18 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Transaction OMBT.
Or path SPRO->Materials Management -> Inventory Management & Physical Inventory -> Number Assignment -> Define number assignment for Material and Phys. Inv. Docs
Note that the year is a 'to year'. So you can even maintain '9999' and then next year you can avoid this problem. Of course assuming that the same number range should apply next year.
Regards,
Dominik Modrzejewski
Thanks Dominik, but my problem is that in tcode-ombt to mention the number range for material doc. there should be a button "+" to insert the new number range for year 2011 or 9999, but that is not present there so i am not getting the way to maintain the new number range for year 2011.
Why it is so?
With Thanks and Regards
Gaurav Kumar Singh