I am using APO V5.1 extended safety stock planning.
For a procured product (procurement type = 'F'), I am trying to clarify the master data used for the calculation of the replenishment lead time.
I assume the planned delivery time at the 'product at location' is used, and the transport lane duration, but what about any parameters from external procurement relationships (eg InfoRecords, contracts) attached to transport lanes - are these considered as well?
Thanks for any advice on this ...
Hi
I think planning already first consider the planned delivery time which is maintained in material master.
Thanks
Amol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
If the Planned delievery time is non zero in the external procurement relationships which reflect in the TL data, then this takes precedence .
In the source determination process in APO, the system uses the planned delivery time to calculate the scheduling of external procurement orders. If there is no entry in the external procurement relationship, or the entry is zero, the system uses the planned delivery time from the product master.
Regards
Datta
Hi,
The replenishment lead time is the time necessary to provide a material either by in-house production or by external procurement:
For external procurement, the replenishment lead time consists of the purchasing department processing time, planned delivery time, and goods receipt processing time
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.