Dear All ,

our Scenario is Make to Stock scenario and we enter PIR (planned independent requirement ) tcode MD61 .

Pl guide for the tcode where we can input the Material wise sales plan in system .

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

hi,

please use MC87 for your purpose.

balajia

Former Member
0 Kudos

thanks for the reply

Pl guide :

1) can we enter the same for multiple materials ?

2) which report displays the entered plan ?

Former Member
0 Kudos

hi,

in that selection screen you are not having an option of entering multiple plants and materials.

so please accept the same and proceeed.

i think no report is there as such you can use MC87 itself for that