on 01-03-2011 11:55 AM
Hi all,
can anybody help me in the following issue....
in a cost project (WBS elements only):
i set up a budget profile (overall & annual years, and availability control against overall values), and assigned it to the project
i configured the availability control in order to issue a error message when exceeding 90% from the budget against all activities (target group: ++)
i activated the Availability Control
However,
When i made an Asset Acquisition (Transaction .F-90) for a particular WBS element with amount more than the WBS element budget, the system permit the transaction and does NOT issue the error message.... WHY??
Also, when i run CJI3 report, i find the amount of the Asset Acquisition in the actual cost of the WBS element, HOWEVER, when i run Budget/Actual/Variance report S_ALR_870133557 i do NOT find the amount in the Actual Cost column.... WHY??
NOTE: the availability control is working well against Purchase Orders, Goods Issues and FI direct postings FB60
May I know why did you use F-90 ? also, what are the line item entries recorded for F-90 in your WBSE.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check up the cost elemnt against which this cost is reflecting in CJI3.Check whther any exmption has been set up for this cost element.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.