Hey guys!

I'm having a problem with the status on the approval of contracts in SRM; even though all the required approvers have checked the contract and approved it, its status still remains at "Waiting for Approval." Would anyone know what might be causing this and how this could be fixed?

Many thanks!

Glenn

Accepted Solutions (1)

Accepted Solutions (1)

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Glenn,

Please try these general check points.

+ SM58 - something tRFC network error

+ RZ20 - something backend or local error

+ BBP_PD - check the document status

Regards,

Masa

Former Member
0 Kudos

Hi Masa,

Should this be automatically approved or this should status be changed manually?

Thanks!

pvanhoove
Product and Topic Expert
Product and Topic Expert
0 Kudos

In addition:

SM13 : error in update task, and check for dump too (ST22)

Rgds

Pierre

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Case,

The problem looks the approver approved workitem but the application document status is waiting for approve. In this case there is some error. You should check what is the error in transaction SM58, RZ20, ST22, SM21, BBP_PD.

You should not change the document status manually.

Regards,

Masa

Former Member
0 Kudos

Oks Thanks Masayuki, How can I give you points if I have not created the topic?