Hi Experts,
While initial uploading vendor , it was maintined for Pur Org 3000 only and same show in BP in Supplier data tab page.
Now in ECC , we extended Vendor from Pur.Org 3000 to 2000 .
I tried programe BBP_VENDOR_SYNC, but don;t seems it update the Vendor Master.
Can anyone please suggest, how to update the extenstion of the Vendor Master or any onter change in SRM from ECC ?
We have SRM7.0
Thanks in advance.
Regards
NAP
Hi
Once you extended purchase organisation for Vendor master , after BBP_VENDOR_SYNC job, it must be updated in SRM.
There are some SAP correction notes if not transfer that you may install in ECC or SRM side.
1113833 - check this note
mUTHU
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you please try the transaction BBPUPDVD on SRM ?