combine pr based on material group

Former Member
0 Kudos

hi all

in our client requirement we need to create pr based on the material group we are doing this process it working fine,in our project we are same material group at many wbs through network activity that time system generated pr at every time for ex same material group is assigned to different wbs in the same project i need to combine all this and need to create only one pr for material group to one wbs

please advise to do.

regards

sen

Accepted Solutions (0)

Answers (3)

Answers (3)

kalpesh_agrawal
Participant
0 Kudos

Hi,

Pl try requirement grouping functinality. You can group wbs's via grm3 or grm4. For that you have to maintan MRP group in material and same need to be assigned to plant in configuration.

Regares,.

Kalpesh

virendra_pal
Active Contributor
0 Kudos

This cannot be done by standard SAP - frankly I cannot see the point of this requirement to raise PR

former_member203108
Active Contributor
0 Kudos

You can change the PR using this exit COZF0002, but I am not user whether you can group the PR according to material group using this exit. Just try it out, check with your ABAPer.