How to stop raising of PR's if sufficient stock is in.

Former Member
0 Kudos

Hi Gurus,

Here i have a problem with Purchase requisition & Reservation.

Im giving Reservation for WBS(Procurement type) & later lm running MRP,then its raising PR even there is stock.

And one more issue is,if im using Reservation+purchase requistion for project,then also its raising PR,for the same material & same stock

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

1. Re+PR procurement indicator will create Pr irrespective of Stock level. - Std SAP

2. MRP project will not check Plant stock level, it will check only project stock level. But, how to make MRP to consider plant stock remains unsolvable, even I had looked up many threads in MM/PP forum with similar requirment, there is no concrete solution for this issue, may be a system design.

Answers (2)

Answers (2)

former_member230675
Active Contributor
0 Kudos

Hi,

The following settings in Material Master also will help to consider an item from commonstock while running Project MRP (MD51).

View : MRP1

MRP Type : PD

Lot Size : MB

*******

View : MRP 2

Procurement Type : F

*******

View : MRP 3

Availability Check : 01

Cross project : 1

*********

View : MRP 4

Individual/coll. : 2

Tnx

Abdul

former_member203108
Active Contributor
0 Kudos

View : MRP 4 , Individual/coll. : 2

If you select '2', then that material is managed at plant stock only not at project stock level. So, the MD51 will not consider that requirement.

Former Member
0 Kudos

Only if you are managing plant stock for your project.You can generate a warning message stating the material is available in the stock

If you material availability check is active and you have mainatined collective requirements in MRP4 view.