Alternative BOM picking at the time of creating sales order.

Former Member
0 Kudos

Dear All,

I have on requirment and it is as follows.

I have 3 alternative BOMS for one material in same plant.Now sales order is created for this materila which alternatibe BOM will system pick.

If there any possibility to customise alternative BOM picking at the time of creating sales order.Please let me know what settings do I need to configure for this.

Thanks for your support and time.

With Rgds,

Babu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

this is to inform you that,

1. since you have 3 alternative BOM's. so by default system will pick up that BOM which is first according to hirearchy level at the plant level.

alternatively if the same material is going to be used for different purpose (PRODUCTION OR PLANNING), SECOND ALTRENATIVE bom will be picked.

2. you will have to assign the BOM which you want to pick add it to the picking list (ASSEMBLY OF THE PRODUCTS/COMPONENTS).

in CO27 - maintain the range of components at component level with plant as same for which you have already created a BOM.

create a sales order according - that alternative BOM will be directly assigned to the sales order.

please check and confirm.

balajia