unable to enter percentage of completion

former_member494495
Active Contributor
0 Kudos

Hi,

After assigning the progress version and clicking Estd values button a new screen "Enter percentage of completion" is opening

But the screen is found greyed out.

How should i enter in it ?

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Also you should have done scheduling, If it is a WBSE check whether Basic Start date, end date and duration are maintained in dates tab, if not then maintain it, now you can assign POC using estimates method

former_member494495
Active Contributor
0 Kudos

thanks

former_member203108
Active Contributor
0 Kudos

you can record actual POC only when actual data's are maintained for the WBSE. So you should release the WBSE and also maintain the actual date(start) in dates tab, now you will be allowed to enter actual POC

Answers (2)

Answers (2)

former_member494495
Active Contributor
0 Kudos

Hi Rafi,

I missed out the Basic date.

Thanks for your answer. I am new to PS module.

former_member203108
Active Contributor
0 Kudos

Have you assigned Estimates as your progress method, atleast in method plan if you are trying to enter Plan POC?