We Want to update fields at Project Level & WBS Level

Former Member
0 Kudos

Dear All,

Actually, we want to update some field at Project level like the start date,End Date & Partner functions.

In addition, we want to update some fields at Header WBS & Child WBS for the same project.

Can anyone suggest that LSMW should work in that situation or any BAPI I have to use.

Thanks

PM

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Try using BAPI's. There is a blog which gives you list of BAPI's available for PS, you can find the link in the first thread of this forum

Answers (2)

Answers (2)

virendra_pal
Active Contributor
0 Kudos

BADI are the best option for updates

For Project Defintion - PROJECTDEF_UPDATE

For WBS - WORKBREAKDOWN_UPDATE

former_member203108
Active Contributor
0 Kudos

You can consider BDC also as an option.

Former Member
0 Kudos

Hi

Thanks for your reply.

Is it possible to create LSMW for CJ20N transaction.

Thanks

PM

former_member203108
Active Contributor
0 Kudos

It would be difficult by using CJ20N, So I would suggest you to use individual transactions like CJ06,CJ11,CJ01 like that.