Dear All,
Actually, we want to update some field at Project level like the start date,End Date & Partner functions.
In addition, we want to update some fields at Header WBS & Child WBS for the same project.
Can anyone suggest that LSMW should work in that situation or any BAPI I have to use.
Thanks
PM
Try using BAPI's. There is a blog which gives you list of BAPI's available for PS, you can find the link in the first thread of this forum
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
BADI are the best option for updates
For Project Defintion - PROJECTDEF_UPDATE
For WBS - WORKBREAKDOWN_UPDATE
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can consider BDC also as an option.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.