I have a question about Planned Costs in the t_code CJR2.
I want to make a CJR2 layout where you can put in the first column the amount of total cost, and 12 columns following 12 months, and that in the first column enter the amount of total for cost element, then will automatically cost distribute that cost me in each of the 12 periods in the others 12 columns.
It can be done by the IMG entry "Create User-Defined Layouts for Detailed Planning Planning (OPO1 )????
Thanks for your answers.
Best Regards.
Yes you can create a new layout for the transaction CJR2 using the IMG node you have specified.
You will need to specify distribution key - with a relevant profile.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Chuso,
Go to the first thread of this forum, you will find list of links useful for PS, in that open the link for PS Wiki, there you will find a wiki created by Sreenivas Kadiam explaining about excel upload of cost plan, in that wiki you will find a link to a blog written by him, this blog will help you to create a user defined layout. Read that blog, and do some practices, you will succeed.