How to assign container resource to routing

Former Member
0 Kudos

Hi,

We have three container resources representing 3 storage tanks with capacity in kilograms. I am not able to assign the storage resources to routing. We are using discrete routing.

Please help.

Thanks,

Andy

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi andrew3,

Container resource functionality is available only in PP-PI manufacturing and not in Discrete manufacturing, because of which you are not able to assign this resources in routings