on 12-23-2010 3:47 PM
Dear Experts ,
I am working on one of support project and my client is getting one error related to workforce planning . i will write you what he is doing step by step
1. He plan the work for certain period in activitys .
2. He go to CMP2 and select activity line and do the personnel assignement and allocate some hours for working weeks and save the data.
At this point he can still delete the assignment.
3. Now he Go to time entry CAT2 and insert some ours for the activity (same person who had the hours assigned in CMP2) and save the data . this stage assignment can be deleted still.
4. Now he do the CATA and tranfer hours to project . now he goes again to CMP2 and wants to delete the assignment but getting error Confirmed assignment cannot be deleted
I just wanted to know its standared behaviour or i need to do some config changes.
Thanx in Advance
Regards
Amit
Amit,
You can reverse the confirmation and delete. Also, try to compare it with other cases, where you can actually delete the person
BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is standard behavior, just think, you assigned resources to your activity, the resources finished the work, the time is recorded and the cost has been booked...now how can you delete it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thamx for your input ,
Actually this a support project and i am new in this project and the guy who has worked on this left out , now when i investigated with client he tolds me basically they assign the person through CMP2 and by mistake some body has performed the CATA and transfer hrs to project but after transfer they found that this was a wrong assignment and now they want to delete him and make a new assignment but at this time work hrs is not completed for the particular week meaning they immediately found there mistake and now change the assignment. they want this fuctionality for this particular event and not for those case where the working hrs completed and actual cost is booked . so my question is there any kind of reversval method so whatever the hrs transfered by mistake can be reversed and then we can delete the assignment in CMP2.