Dear all,
Here in availbility check for third party material and every material the material availability is showing after 7 days at the time of purchase requisition.
To analyze the same we gave no check code in material master and planned delivery time also made zero but still while the creation of SO, purchase requisition is triggered after 7 days.
but when we checked the purchase requisition processing time .. there it is 3 days was mentioned,
why this thing is included in the scope of check?
regards,
archu
s
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
as suggested by Balaji maintain the lead time or next ti that there is field called as Propose current date as purchase order date if you maintain this check box then system automatically proposes the current date as the purchase order date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi archana,
goto VOV8 - OR or the sales document which have been used for PR generation and check lead time in days.
check and confirm
balajia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.