Hi All,
We are facing issue of PO scheduling in ECC & APO----
-- In ECC, system calculates requirement date with planned delivery time +GR processing time but during addition of GR processing time it excludes weekends( Saturday & Sunday) However in APO, system calculates requirement date by addition of GR processing time in the planned delivery time but it includes weekends & eventually requirement date mismatch.
-- Secondly we are using handling resource for scheduling purpose in APO but we found start time is different for differnent handling resources e.g. 14.00,16.00 ,from where the system picks up the timings
-- In APO product master ,GR processing time is 1 day but during PO scheduling, system picks 3 days & calculats requirement date ,its strange for me
Is there any way out for above mentioned issues
Thanks in advance for your help
Kind regards
Milind
Hi,
Please check the factory calendars and time stream ids. The working schedule of APO should match with ECC.
The location master also needs to be checked for what time stream is attached there and what is the working schedule.
Thanks,
Chan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.