12-22-2010 7:51 PM
Dear SAP.
I Need help. We use the old version of FM (FBS) and by necessity (New Objet: Program budget) was needed to activate the BCS. It Was made all the migration but when we release bursts in the envelope in the message two (former budget and BCS - Item FMAVC005 - Budget payment, and Item BP629 exceeded budget payment execceded) or should only be checking the new version of BCS
Any help will be very welcome
Sorry, my english is bad.
Best Regards
Marck - Brasil
12-22-2010 9:02 PM
Hi,
'but when we release bursts in the envelope in the message two'-please clarify. When messages appear,and what long text
12-22-2010 9:02 PM
Hi,
'but when we release bursts in the envelope in the message two'-please clarify. When messages appear,and what long text
12-23-2010 12:20 PM
Hi, you should deactivate your settings from Former Budgeting if you have activated BCS.
Kind regards
Mar
01-03-2011 7:24 PM
Dear Mar, why deactive former budgett ? (FMFBS). Because a BCS is active in my system.
They are is not using former budget.
01-05-2011 11:18 AM
Hi,
If you are using BCS, the settings from former budgeting should not be used any longer. For instance, Availability control is technically different in BCS than in Former Budgeting (different tables).
so, if AVC is already active in BCS because BCS is active and configured, you should switch AVC Off in Former Budgeting.
You should choose only BCS settings.
Let me know if I have understood your query
Kind regards,
Mar
01-12-2011 11:13 PM
Dear Mar
Who AVC Off in Former Budgeting ?
Please, have sender who disable Former budget ?
Thank
01-13-2011 12:07 PM
Dear Mar,
sorry - me, that reads like "Who" the correct "where".
Thank you
01-13-2011 2:59 PM
Hi,
First, please check your settings for Availability Control in the IMG path
Funds Management Government->Former Budgeting->Availability Control_>Deactivate/Activate Availability Control
If you have BCS, the AVC is performed according to the customizing of BCS. Therefore the above mentioned path is no longer relevant and the AVC should no longer be switched on there.
cheers
Mar
01-18-2011 10:24 AM
Mar,
Please do you know further details on when SAP will end support to former budgeting solution.
Clients are always asking this information and I don't find this anywhere.
Many thanks,
Best regards,
01-24-2011 4:14 PM
hello
Former Budgeting will continue to be supported, however not enhanced since the strategic tool for budgeting is BCS.
But customers using Former Budgeting will continue to receive support as part of their support mainstream.
Hope this answers your question
Kind regards
Mar